(Alamanda) Fit Out Guidelines - Mall Requirements for Hoarding, Visual & Reinstatement
- hG Group Enquiry MY
- 13 hours ago
- 2 min read
DISCLAIMER: Please note that these guidelines may change without prior notice; we will do our best to update the information as frequently as possible. The information below is intended for your reference only. For the most accurate and detailed information, please contact the mall's fit-out team directly. MALL's DETAILS
1. | Mall's Name | Alamanda | |
2. | Mall's Co. Name | Putrajaya Holdings Sdn Bhd | |
3. | Location | Putrajaya |
HOARDING & VISUAL (Indoor Lot & Kiosk) REQUIREMENTS
1. | Hoarding Material | MDF | NOTES: Marine Plywood (Proposed Material If Outdoor Hoarding - Expose to Weather) |
2. | Hoarding Structure | Timber | |
3. | Hoarding Door Type | Sliding Door | 1500mm x 2100mm |
4. | Add-On (Counterweight) | a. For Kiosk (Free-Stand) b. Outdoor hoarding (Expose to Wind Load) c. Hoarding Height exceed 5meter | |
5. | Add-On (Fabric) | Top Fabric Surface Cover | For Lot & Kiosk |
5. | Hoarding (Kiosk) Height | 2440mm (8ft) | |
6. | Hoarding Visual Material | Sticker Only | By Mall Panel Only |
7. | Skirting | 2inch (Bottom Only) |
NOTES: Click HERE for sample hoarding and/or visual installation at Alamanda for your reference
MALL FIT OUT GUIDELINES
1. | Safety Pledge | Valid for 3 months NOTES: Compulsory for all site personnel & workers to attend safety briefing at security office to obtain safety pledge before start work on-site. Set appointment prior before attending the safety briefing. |
2. | Site Dilapidation Picture(s) | Make sure take pictures of existing site condition before start work to avoid any dispute later. |
3. | Floor Protection On-Site | Compulsory installation of floor protection at common walkway area for trolleys & workers mobilization during on-site work and clear off & clean up on daily basis after daily job done. |
4. | CIDB Green Card | Worker(s) compulsory to have CIDB Green Card in order to work within the mall. |
For on-site worker(s) to access WORK AT HEIGHT, it is compulsory under mall safety requirement to use ALUMINIUM SCAFFOLD with GREEN TAG tagging which inspect by AUTHORIZED & COMPETENT SCAFFOLD INSPECTOR. |
REINSTATEMENT GUIDELINES
1. | Preliminaries | Site Arrangement & Documents Preparation |
2. | Insurance | RM2mil Public Liability |
3. | Reinstatement | Dismantle, Demolish, Move Out, Clear Off |
4. | Rorobin (RRB) | Engage by Contractor(s), To Clear Out from Mall Loading Bay Area before 6am Daily (STRICTLY NO OVERNIGHT) |
5. | 3rd Party Panel Contractor(s) | a. Sprinkler b. Wet Chemical (If Have, for F&B Lot/Kiosk Only) c. LPG (If Have, for F&B Lot/Kiosk Only) d. Telephone Line e. PA Speaker f. Flushing (If Have Floor Trap within the Lot/Kiosk) g. Tiles Replacement (Supply & Install) |
6. | Touch Up and/or Restoration | After Site Inspection by Mall Fit Out Team (IF REQUIRED ONLY based on Lot Condition) Frequent Restoration Item(s) as Listed Below: 1. Wall (Skim, Plastering & White Painting) 2. Ceiling (Plastering & Painting) 3. Tiles Replacement Lease Line Area (by Mall Panel Only) 4. Internal Lot Pelmet Close Up using Gypsum Board 5. Floor Tiles/Marble Polishing 6. Sprinkler (Level 1 - Paint RED) 7. Telephone Box (To Replace / Relocate Back to Original) 8. Isolator (To Replace / Relocate Back to Original) |